NEW QUESTION # 331
According to the Theory of Constraints, which of the following statements is true?
- A. Use of Drum-Buffer-Rope includes communication from the bottleneck to the Gateway workcenter
- B. A buffer of inventory should always be maintained after the bottleneck.
- C. Constraints always exist in a factory
- D. Work centers feeding bottlenecks should operate at peak utilization to ensure WIP availability at all times.
Answer: A
NEW QUESTION # 332
Which one of the following tools that cannot be used to evaluate feasibility of a strategy?
- A. Cash flow analysis and forecasting
- B. Break-Even analysis
- C. None of these
- D. Resource deployment analysis
Answer: C
NEW QUESTION # 333
Which of the following are the types of sourcing?
- A. Sole, Group
- B. Multiple, single
- C. Sole, multiple, single
- D. Group, multiple, single
Answer: C
NEW QUESTION # 334
is responsible for producing a set of specifications that manufacturing can use to make the product. Products must be designed to be:
* Functional
* Capable of low-cost processing
- A. All of these
- B. Production Plan
- C. Marketing mix
- D. Product Design
Answer: D
NEW QUESTION # 335
Goods or services satisfy the needs and expectations of the user, this refers to:
- A. Quality
- B. Reliability
- C. Stability
- D. Maintainability
Answer: A
NEW QUESTION # 336
The purpose
change.
- A. Scheduling plan
- B. Strategic business plan
- C. Change management plan
- D. Production plan
Answer: B
NEW QUESTION # 337
Which of the following plant is used in the production process, where few raw materials can be made into several end products?
- A. V-plant
- B. A-plant
- C. G-plant
- D. I-plant
Answer: A
NEW QUESTION # 338
The sum of queue, setup, run, wait and move times is known as:
- A. Principal time
- B. Lead time
- C. Guide time
- D. Direct time
Answer: B
NEW QUESTION # 339
When items required from stock must be selected from storage and brought to a marshalling area, this activity is called:
- A. Collect goods
- B. Select goods
- C. Accept goods
- D. Pick goods
Answer: D
NEW QUESTION # 340
A price that is competitive, gives the seller a profit, and allows the buyer ultimately to sell at a profit is known as:
- A. Fair price
- B. Impartial price
- C. Actual price
- D. Average price
Answer: A
NEW QUESTION # 341
Production must keep its operating cost as low as possible this can be done in the following way/ways:
- A. Make long production runs of relatively few production runs of relatively few products. Fewer Changeovers will be needed and specialized equipment can be used thus reducing the cost of making the product
- B. Provide lowest distribution costs
- C. Maintain high inventories of raw materials and work-in-process so production is not disrupted by shortages.
- D. Manufacture only to customer order
Answer: A,C
NEW QUESTION # 342
Which one of the following is NOT done by PAC in control phase?
- A. Report work center efficiency, operation times, order quantities and scrap.
- B. Track the actual performance of work orders and compare it to planned schedules.
- C. Ensure that required materials, tooling, personnel and information are available.
- D. Monitor and control work-in-process, lead times, and work center queues.
Answer: C
NEW QUESTION # 343
The ranking of jobs for the dispatch list is created through the application of which of the following priority rule?
- A. Shortest process time
- B. All of the above
- C. Earliest operation due date
- D. First come, first served
Answer: B
NEW QUESTION # 344
Over the previous four weeks, a work center produced 120, 130, 150,140 standard hours of work. What is the demonstrated capacity of the work center?
- A. 130 standard hours
- B. 140 standard hours
- C. 135 standard hours
- D. 139 standard hours
Answer: C
NEW QUESTION # 345
The time needed to perform operation is an important input factor to the manufacturing planning and control system. It is needed to schedule work through the plans,
- A. And cost the product
- B. Load the plant
- C. Make delivery promises
- D. All of these
Answer: D
NEW QUESTION # 346
Inventory investment can be balanced with:
- A. Cost of placing orders
- B. Customer service
- C. All of the above
- D. Costs associated with changing production levels
Answer: C
NEW QUESTION # 347
A work center has 3 machines and is operated for 8 hours a day and 5 days a week. What is the available time?
- A. 120 hours per week
- B. 80 hours per week
- C. 90 hours per week
- D. 100 hours per week
Answer: A
NEW QUESTION # 348
In back scheduling, Sequence of operation, Work centers needed setup time, and runtime are included in a/an?
- A. Load Sheet
- B. Route file
- C. Order file
- D. Work Center file
Answer: B
NEW QUESTION # 349
There are following reasons of using sample inspections:
- A. Testing the product is destructive
- B. It is too expensive to test the entire batch and human errors is to be estimated as high as 20%
- C. All of these
- D. There is not enough to give 100% inspection to a batch of product
Answer: C
NEW QUESTION # 350
Which of the following is NOT the role that warehouses serve?
- A. Cubic space
- B. Service
- C. Transportation consolidation
- D. Product mixing
Answer: A
NEW QUESTION # 351
A routing file should contain the following information EXCEPT:
- A. Sequence of operations
- B. Work centers to be used
- C. Priority plan
- D. Operations to be performed
Answer: C
NEW QUESTION # 352
With the explosive growth in just-in-time (JIT) concepts, the supplier-customer partnership concept grew as a result many changes in their relationships came including:
- A. Mutual product design
- B. Mutual analysis for cost reduction
- C. Need for rapid delivery
- D. Speed of accurate information flow
Answer: D
NEW QUESTION # 353
The orders are automatically scheduled and controlled by the computer are the orders called:
- A. Firms planned order
- B. All of the Above
- C. Computer generated order
- D. Planned orders
Answer: D
NEW QUESTION # 354
Metrics give us:
- A. Control by supervisors
- B. Product description
- C. Reporting of data to supers and external description
- D. Process specification
Answer: A,C
NEW QUESTION # 355
The formula for the seasonal demand is:
- A. Seasonal demand = (seasonal index) - (deseasonalized demand)
- B. Seasonal demand = (seasonal index) + (seasonalized demand)
- C. Seasonal demand = (seasonal index) / (deseasonalized demand)
- D. Seasonal demand = (seasonal index) * (deseasonalized demand)
Answer: D
NEW QUESTION # 356
......